Naval Support Activity Mechanicsburg
Mechanicsburg, PA
Huen reworked the entire power distribution system in Buildings 312 and 410. We ran new 13.2 kV power from the nearby manholes to the buildings as part of the complete rebuild. We also replaced the interior distribution equipment including the main medium voltage HVL switches, cast coil transformers, distribution switchboards and sub panels. The project required us to work in phases after hours to leave the building ready for daily use.